Automotive Production Readiness Accelerated by 5 months

The Challenge
The external customer’s manufacturing facilities were using legacy on-premise systems to collect data from over 60 machines and 30 different equipment types. Three hundred components were built into one million systems per year using a complex sixty-three step process. Adopting the existing on-premise systems would necessitate an extensive eight month project to understand the legacy software, the equipment protocols and replicate the same approach in Tatabanya. However, production had to begin in only three months!
Why 42Q
Sanmina had already used 42Q to connect more than 35,000 pieces of equipment to the cloud and had developed significant expertise in developing APIs to consolidate the data from a diverse range of equipment.

Results
- An innovative, complex integration platform was developed in 3 weeks.
- 42Q was production ready in only 4 weeks.
- Production started on schedule in only 3 months.